Question: An assembly line has three work stations A, B and C. The materials move from A to B and then to C. Station A takes
An assembly line has three work stations A, B and C. The materials move from A to B and then to C. Station A takes 3 minutes, B 6 minutes and C 1 minute.
What is the cycle time (in minutes)?
| 1 | ||
| 3 | ||
| 6 | ||
| 10 |