Question: An operations manager needs to develop a production plan. Using a chase strategy with the following 4 month demand and starting employee count, how many
An operations manager needs to develop a production plan. Using a chase strategy with the following 4 month demand and starting employee count, how many employees will be fired and how many will be hired if each employee can fix 20 engines per period?
Starting Employee Count = 90
November = 2120
December = 2160
January = 1460
February = 1240
| 13 and 16 | ||
| 18 and 46 | ||
| 12 and 12 | ||
| 18 and 48 | ||
| 12 and 14 |