Question: An operations manager needs to develop a production plan. Using a chase strategy with the following 4 month demand and starting employee count, how many

An operations manager needs to develop a production plan. Using a chase strategy with the following 4 month demand and starting employee count, how many employees will be fired and how many will be hired if each employee can fix 20 engines per period?

Starting Employee Count = 90

November = 2120

December = 2160

January = 1460

February = 1240

13 and 16

18 and 46

12 and 12

18 and 48

12 and 14