Question: Answer the question in 5 minute The following represents a project that should be scheduled using CPM: b. What is the critical path? A-D-G-H B-E-G-H

Answer the question in 5 minute
The following represents a project that should be scheduled using CPM: b. What is the critical path? A-D-G-H B-E-G-H A-D-F-H A-C-F-H c. What is the expected project completion time? (Do not round intermediate calculations. Round your answer to 3 decimal places.) d. What is the probability of completing this project within 16 days? (Use Excel's NORM.S.DIST() function to find the correct probability for your computed Z-value. Do not round intermediate calculations. Round " z " value to 2 decimal places and final answer to 4 decimal places.)
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock