Question: ASAP The critical path for the network activities shown below is with duration P-Y-Z; 14 months Q-Z; 4 months Q-X-Z; 5 months Q-P-Y-X-Z; 17 months
ASAP
The critical path for the network activities shown below is with duration P-Y-Z; 14 months Q-Z; 4 months Q-X-Z; 5 months Q-P-Y-X-Z; 17 months Q-Y-Z; 10 months P-X-Z; 9 months