Question: The critical path for the network activities shown below is ________ with duration ________. Activity Duration (Month) Immediate Predecessors Q 2 -- P 6 --

The critical path for the network activities shown below is ________ with duration ________.

Activity Duration (Month) Immediate Predecessors
Q 2 --
P 6 --
Y 6 P, Q
X 1 P, Q
Z 2 Q, Y, X

Question 37 options:

P-Y-Z; 14 months

Q-Z; 4 months

Q-X-Z; 5 months

Q-P-Y-X-Z; 17 months

Q-Y-Z; 10 months

P-X-Z; 9 months