Question: The critical path for the network activities shown below is ________ with duration ________. Activity Duration (Month) Immediate Predecessors Q 2 -- P 6 --
The critical path for the network activities shown below is ________ with duration ________.
| Activity | Duration (Month) | Immediate Predecessors |
| Q | 2 | -- |
| P | 6 | -- |
| Y | 6 | P, Q |
| X | 1 | P, Q |
| Z | 2 | Q, Y, X |
Question 37 options:
| P-Y-Z; 14 months | |
| Q-Z; 4 months | |
| Q-X-Z; 5 months | |
| Q-P-Y-X-Z; 17 months | |
| Q-Y-Z; 10 months | |
| P-X-Z; 9 months |
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
