Assignment: Arrow Diagram Method Activity

Assignment: Arrow Diagram Method Activity Duration (days) A 1 B 2 3 D 4 E 5 F 6 G 6 H 6 I J Based on the table above, Predecessor A B C D, E 2 G 3 F, H, I a. Develop an arrow diagram for the project b. Identify the critical activity and critical path for the project.