Question: The following table represents a project that should be scheduled using CPM. ACTIVITY IMMEDIATE PREDECESSORS Activity Duration (Days) A 1 B 3 C A 1
The following table represents a project that should be scheduled using CPM.
| ACTIVITY | IMMEDIATE PREDECESSORS | Activity Duration (Days) |
| A | 1 | |
| B | 3 | |
| C | A | 1 |
| D | A | 2 |
| E | B | 3 |
| F | C, D | 3 |
| G | D, E | 1 |
| H | F, G | 2 |
The critical path is
The length of the critical path in question 1 is
The duration of the project in question 1 is days.
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
