Question: The following table represents a project that should be scheduled using CPM. ACTIVITY IMMEDIATE PREDECESSORS Activity Duration (Days) A 1 B 3 C A 1

The following table represents a project that should be scheduled using CPM.

ACTIVITY

IMMEDIATE PREDECESSORS

Activity Duration (Days)

A

1

B

3

C

A

1

D

A

2

E

B

3

F

C, D

3

G

D, E

1

H

F, G

2

The critical path is

The length of the critical path in question 1 is

The duration of the project in question 1 is days.