Question: Assuming that all future work will be performed at the budgeted rate, the estimate to complete (ETC) is: ( Cumulative Data for question: BAC =
Assuming that all future work will be performed at the budgeted rate, the estimate to complete (ETC) is: (Cumulative Data for question: BAC = 300, PV = 200, AC = 120, EV = 70)
a.
180
b.
230
c.
130
d.
110