Question: Given that BAC = 180, PV = 100, AC - 120 and EV - 80 and that all future work will be performed at the

Given that BAC = 180, PV = 100, AC - 120 and EV -
Given that BAC = 180, PV = 100, AC - 120 and EV - 80 and that all future work will be performed at the budgeted rate, the estimate at completion (EAC) is 200 220 d. 240 d. 260