Question: ( b ) A project manager discovers that his team has neglected to complete the network diagram for the project. The network shown in Figure
bA project manager discovers that his team has neglected to complete the network diagram for the project. The network shown in Figure Q However, the project manager has some information available, specifically that each activity, labe has a different duration between one and seven weeks. Also, the slack time for each of the activities is known in Table
Table Q
Duration we
Slack time wt
Figure Q
Clues
There exists only one critical path, and it is the largest possible number given the possible durations shown.
Activity E has the smallest amount of slack that is greater than zero.
The early finish EF time for activity A is four weeks, and this does not equal the latest finish LF time. Note: The negative slack in the network.
The slack in activity C is eight weeks.
The duration of activity F is greater than the duration of activity C by at least two weeks
Using the clues provided below,
i Determine the duration of each activity
ii Calculate the early start, early finish, latest start, and latest finish times for each activity.
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock