Question: b. Calculate the slack for each activity. Which activities are on a critical path? A project for improving a billing process has the following precedence

b. Calculate the slack for each activity. Which

b. Calculate the slack for each activity. Which activities are on a critical path?

A project for improving a billing process has the following precedence relationships and activity times: Activity Time (weeks) Immediate Predecessor(s) 4 10 8 Activity B D E F G H A B.C 14 9 5 6 6 B D E F G a. Choose the correct network diagram below. . OB. S S oc. OD E S 10