Question: A project for improving a billing process has the following precedence relationships and activity times: Activity Activity Time ( weeks ) Immediate Predecessor ( s
A project for improving a billing process has the following precedence relationships and activity times:
Activity
Activity Timeweeks
Immediate Predecessors
A
minus
B
minus
C
A
D
B C
E
B
F
D
G
E
H
b Calculate the slack for each activity. Which activities are on the critical path?
Activity
Activity Time weeks
On critical path?
Slack weeks
A Yes B No C Yes D Yes E No F Yes G No H Yes A project for improving a billing process has the following precedence relationships and activity times: