Question: b. The table given below indicates five jobs A, B, C, D, and E along with their processing times and delivery dates. Calculate the avg.

b. The table given below indicates five jobs A,
b. The table given below indicates five jobs A, B, C, D, and E along with their processing times and delivery dates. Calculate the avg. lateness and avg. flow time for each job using Critical ratio and Earliest Due Date (EDD) methods. Jobs AB C DE Processing time in days 7 50 9 6 18 Due date in days 10 6 17 14 27