Question: B/9 E15 A/11 CIT G14 F/9 D/6 e For each of the seven tasks that make up the project above, assume the following: Percent Actual

B/9 E15 A/11 CIT G14 F/9 D/6 e For each of the

B/9 E15 A/11 CIT G14 F/9 D/6 e For each of the seven tasks that make up the project above, assume the following: Percent Actual TASK Complet Expendit Expenditures Duration ures/Day to Date A 10074 $2,000 $10,000 11 B 100% $1,200 $9,000 9 C 30% $1,000 $4,000 7 D 20% $1,500 $5,000 6 E 40% $1,500 $3,000 5 F 02 $1,000 $0 9 G 02 $1,200 $0 4 TOTAL ACWP BCWS BCWP TASK ZCOMP CV SV CPI BUDGET SPI (AC) (PV) (EV) A $22,000 100% $10,000 B 100% $9,000 C 30% $4,000 D 20% $5,000 E 40% $3,000 F 02 $0 G 07 $0 Totals For each task and for the entire project (bottom line) calculate BCWS, BCWP, CV, SV, CPI, SPI. Project is 14 days old--14 business days have transpired. BAC = TAC = EAC = ETAC = Comments on the status of your project

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!