Question: Use the baseline plan presented here to complete the progress update provided at the end of the 6th period, and then answer the questions that

Use the baseline plan presented here to complete the progress update provided at the end of the 6th period, and then answer the questions that follow: (critical tasks are in red/bold fonts) Baseline Plan Task Budget 1 2 3 4 5 6 7 7 8 00 9 10 11 12 13 A 2000 1000 1000 B 2400 1200 1200 3000 500 500 500 500 500 500 D 2500 500 500 500 500 500 E 1600 400 400 400 400 F 2000 500 500 500 500 G G 1000 500 500 Cumulative Update at the end of 6th Period: Progress Update Task % Complete EVAC PV CV SVCPI SPI A 100% 1500 B 100% 2000 C 70% 2100 D 80% 1800 E 1000% 600 Cumulative Totals 8000

The budget at completion for this project is:

Based on the baseline plan, this project is expected to finish by period

The earned value (EV) of task C at this point is is:

The cumulative planned value (PV) is:

The cumulative SPI is:

Based on information you have thus far, it is reasonable to conclude that the project will be completed ___________ the date that was originally communicated as the its completion date.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!