Question: Use the baseline plan presented here to complete the progress update provided at the end of the 6 th period, and then answer the questions
Use the baseline plan presented here to complete the progress update provided at the end of the th period, and then answer the questions that follow. Critical tasks are in redbold fonts.
Baseline Plan
Task Budget
A
B
C
D
E
F
G
Cumulative
Update at the end of th period:
Task Complete EV AC PV CV SV CPI SPI
A
B
C
D
E
Cumulative Totals
A The budget at completion for this project is: Enter a number without $ or :
B Based on the baseline plan, this project is expected to finish by period Enter a number without any units
C The Earned value EV of task C at this point is: Enter a number without $ or :
D The cumulative cost variance CV is: Enter a number without $ or :
E The cumulative SPI is: Enter a number with two digits after the decimal, for example: :
F Based on information you have thus far, it is reasonable to conclude that the project will be completed the date that was originally communicated as the completion date. Enter one of the following choices: before, on after
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
