Question: Use the baseline plan presented here to complete the progress update provided at the end of the 6 th period, and then answer the questions

Use the baseline plan presented here to complete the progress update provided at the end of the 6th period, and then answer the questions that follow. (Critical tasks are in red/bold fonts.)
Baseline Plan
Task Budget 12345678910111213
A 200010001000
B 240012001200
C 3000500500500500500500
D 2500500500500500500
E 1600400400400400
F 2000500500500500
G 1000500500
Cumulative
Update at the end of 6th period:
Task % Complete EV AC PV CV SV CPI SPI
A 100%1500
B 100%2000
C 65%2100
D 80%1800
E 50%600
Cumulative Totals 8000
A. The budget at completion for this project is: (Enter a number without $ or ,):
B. Based on the baseline plan, this project is expected to finish by period (Enter a number without any units)
C. The Earned value (EV) of task C at this point is: (Enter a number without $ or ,):
D. The cumulative cost variance (CV) is: (Enter a number without $ or ,):
E. The cumulative SPI is: (Enter a number with two digits after the decimal, for example: 1.56):
F. Based on information you have thus far, it is reasonable to conclude that the project will be completed ___________the date that was originally communicated as the completion date. (Enter one of the following choices: before, on, after )

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!