Question: Based on the following table, a) Draw the network for supposed processes b) Calculate ES, EF, and the project duration Activity Description Predecessors Time (days)
Based on the following table,
a) Draw the network for supposed processes
b) Calculate ES, EF, and the project duration
| Activity | Description | Predecessors | Time (days) |
| A | initial market evaluations | - | 2 |
| B | R&D | A | 3 |
| C | Supply of production materials and equipment | B | 2 |
| D | scale up | C | 3 |
| E | obtaining legal permits | D | 5 |
| F | launch to market | D, E | 4 |