Question: Based on the network diagram below, calculate the early start and early finish, late start and late finish for Activity K , and select the

Based on the network diagram below, calculate the early start and early finish, late start and late finish for Activity K, and select the correct answer.
Question 22 options:
a)
Early start: 29, Early finish: 31;
Late start: 29, Late finish: 31.
b)
Early start: 29, Early finish: 32;
Late start: 35, Late finish: 38.
c)
Early start: 29, Early finish: 31;
Late start: 36, Late finish: 38.
d)
Early start: 29, Early finish: 32;
Late start: 29, Late finish: 32.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!