Question: Based on the table below, identify the activities on the critical path. Activity Duration IPA A 2 none B 3 A C 2 A D

  1. Based on the table below, identify the activities on the critical path.

    Activity Duration IPA
    A 2 none
    B 3 A
    C 2 A
    D 5 B, C
    E 3 C
    F 2 D, E

    A, C, D, F

    A, B, D, E

    B, D, F

    A, C, D, F