Question: Below is an activity network with times (in weeks) shown above each node: Which of the following statements is FALSE? Multiple Choice The critical path

Below is an activity network with times (in weeks) shown above each node: Which of the following statements is FALSE? Multiple Choice The critical path is A.C.E-H. The earliest start time for Activity A is zero since it is the first activity. The slack time Activity His zero. The latest start time of Activity H is 21 weeks. Below is an activity network with times (in weeks) shown above each node: Which of the following statements is FALSE? Multiple Choice The critical path is A.C.E-H. The earliest start time for Activity A is zero since it is the first activity. The slack time Activity His zero. The latest start time of Activity H is 21 weeks