Question: TB MC Qu. 19-28 Below is an activity network with times Below is an activity network with times (in weeks) shown above each node: B

 TB MC Qu. 19-28 Below is an activity network with timesBelow is an activity network with times (in weeks) shown above each

TB MC Qu. 19-28 Below is an activity network with times Below is an activity network with times (in weeks) shown above each node: B F 5 G What is the critical path? Multiple Choice O A-B-D-F-HWhat is the critical path? Multiple Choice O A-B-D-F-H O A-B-E-F-H O A-B-E-G-H O A-C-G-H