Question: Below is the information on a small project. All information is in days and the crash time is the amount of time that the project

Below is the information on a small project. All information is in days and the crash time is the amount of time that the project can be shortened along with the associated cost of crashing.
\table[[Activity,\table[[Time],[In Days]],\table[[Immediate],[Predecessor(s)]],\table[[Crash Time],[(Days)]],Crash Cost],[P,9,none,1,$400? Day],[L,5,P,2,$100? Day],[I,8,P,1,$150? Day],[N,9,L,I,1,$200? Day],[K,4,N,I,2,$500? Day]]
Hint: In order to be successful in this activity you must draw out the AON diagram on your own in order best answer the following questions.
What is the most economical way to reduce the project time (crash) by 2 days.
I-$150,L-$100
K-$500
I-$150,N-$200
L-$100
L-$200
Any of these can be correct as long as we reduce by 2 days.
1-$300
 Below is the information on a small project. All information is

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!