Question: By using the information in above table, draw activity on arrow (AOA) network diagram , including information such as event number, earliest date, latest dated
By using the information in above table, draw activity on arrow (AOA) network diagram, including information such as event number, earliest date, latest dated and slack.

\begin{tabular}{|l|l|l|l|} \hline Activity & Description & Immediate Predecessor & Duration (Hours) \\ \hline A & Receiving Raw Material & & 0.5 \\ \hline B & Bolt cutting & A & 1.0 \\ \hline C & Transfer machine(series of drilling \& cutting operations) & B & 1.5 \\ \hline D & Transfer machine(barrels) & B & 1.4 \\ \hline E & Barrel pinning & D & 1.2 \\ \hline F & Shackle groove cutting & B & 0.8 \\ \hline G & Shackle bending & F & 1.0 \\ \hline H & Insert shackle into body & C,G,E & 1.4 \\ \hline I & Insert barrel into body and test key set & H & 0.5 \\ \hline J & Packaging of padlock & I & 1.4 \\ \hline \end{tabular}
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts