Question: Software Project Management By using the information in above table, draw activity on arrow (AOA) network diagram, including information such as event number, earliest date,

Software Project Management

By using the information in above table, draw activity on arrow (AOA) network diagram, including information such as event number, earliest date, latest dates etc.

Fill the Table

Software Project Management By using the information in above table, draw activity

on arrow (AOA) network diagram, including information such as event number, earliest

\begin{tabular}{|l|l|l|l|} \hline Activity & Description & Immediate Predecessor & Duration (Hours) \\ \hline A & Receiving Raw Material & & 0.5 \\ \hline B & Bolt cutting & A & 1.0 \\ \hline C & Transfer machine(series of drilling \& cutting operations) & B & 1.5 \\ \hline D & Transfer machine(barrels) & B & 1.4 \\ \hline E & Barrel pinning & D & 1.2 \\ \hline F & Shackle groove cutting & B & 0.8 \\ \hline G & Shackle bending & F & 1.0 \\ \hline H & Insert shackle into body & C,G,E & 1.4 \\ \hline I & Insert barrel into body and test key set & H & 0.5 \\ \hline J & Packaging of padlock & I & 1.4 \\ \hline \end{tabular} \begin{tabular}{|l|l|l|l|l|l|l|l|l|} \hline Activity & Duration(Hours) & Earliest Start Date & Latest Start Date & Earliest Finish Date & Latest Finish Date & Total Float & Free Float & Interfer Float \\ \hline A & & & & & & & & \\ \hline B & & & & & & & & \\ \hline C & & & & & & & & \\ \hline D & & & & & & & & \\ \hline E & & & & & & & & \\ \hline F & & & & & & & & \\ \hline G & & & & & & & & \\ \hline H & & & & & & & & \\ \hline I & & & & & & & & \\ \hline J & & & & & & & & \\ \hline \end{tabular}

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Databases Questions!