Question: Case Study 1 : Project Schedule Management: Activity definition & sequencing - - : For the case study project allocated to your team, prepare the
Case Study : Project Schedule Management:
Activity definition & sequencing:
For the case study project allocated to your team, prepare the list of activities.
These activities must be linked to work packages
Detail some components of the Activity Attributes that should include:
a Activity Id
b WBS Id
c Activity Name
d Activity Description
e Predecessor Activities
f Successor Activities
Any other details that may be relevant for understanding the activities.
Format and presentation Style:
Title or Cover Page:
Professional Style
Table of Contents
Purpose of Creating Activity Definition and sequencing activities
Contribution of Team Members with remarks from Team Lead
Summary or Background Information:
Write about the Case Study or Project in hand
WBS:
o Created During Assignments
Activity List:
o List all activities involved in Your Project
o SAMPLE ACTIVITY List
Stamping
Activity Uncoilingblanking aluminum coils
Using the blanking machine, this activity consists of uncoiling the
aluminum coils to be later stamped and cut them into pieces blanks
using laser.
Activity Press lines
This activity consists of essentially form the panels and other ModelS
aluminum pieces main pieces by pressing them into the pressing
lines.
Activity Ironing
In this activity, the material is squeezed and reduced in thickness along a
vertical wall.
Activity Hemming
This activity consists of hamming the ModelS doors edges. This process
includes folding an edge over to add thickness.
Step by Step Solution
There are 3 Steps involved in it