Question: Case Study 1 : Project Schedule Management: Activity definition & sequencing - - : For the case study project allocated to your team, prepare the

Case Study 1: Project Schedule Management:
Activity definition & sequencing--:
For the case study project allocated to your team, prepare the list of activities.
1. These activities must be linked to work packages
2. Detail some components of the Activity Attributes that should include:
a. Activity Id
b. WBS Id
c. Activity Name
d. Activity Description
e. Predecessor Activities
f. Successor Activities
3. Any other details that may be relevant for understanding the activities.
Format and presentation Style:
Title or Cover Page:
Professional Style
Table of Contents
Purpose of Creating Activity Definition and sequencing activities
Contribution of Team Members with remarks from Team Lead
Summary or Background Information:
Write about the Case Study or Project in hand
WBS:
o Created During Assignments
Activity List:
o List all activities involved in Your Project
o SAMPLE ACTIVITY List
2.1.1 Stamping
Activity 23- Uncoiling/blanking aluminum coils
Using the blanking machine, this activity consists of uncoiling the
aluminum coils to be later stamped and cut them into pieces (blanks)
using laser.
Activity 24- Press lines
This activity consists of essentially form the panels and other Model-S
aluminum pieces (14 main pieces) by pressing them into the pressing
lines.
Activity 25- Ironing
In this activity, the material is squeezed and reduced in thickness along a
vertical wall.
Activity 26- Hemming
This activity consists of hamming the Model-S doors edges. This process
includes folding an edge over to add thickness.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!