Question: CASE STUDY As project manager, you have gathered the information in the below in the process of tracking your cost and progress of work package
CASE STUDY
As project manager, you have gathered the information in the below in the process of tracking your cost and progress of work package A:
Project Sub[1]Account / work package - A
BCAC - 24000
ACWP - 13000
BQAC - 500
AQWP - 300
Percentage complete (50%)
OD - 24
BCWS - 14500
Now answer the questions below,
Based on the information above.
1.1. BCAC = R24 000; BCWS = R14 500; ACWP = R13 000; and SV = -2 500.
What is the planned value of the work that was done?
A. R14200
B. R14500
C. R24000
D. R13 000