Question: CASE STUDY As project manager, you have gathered the information in the below in the process of tracking your cost and progress of work package

CASE STUDY

As project manager, you have gathered the information in the below in the process of tracking your cost and progress of work package A:

Project Sub[1]Account / work package - A

BCAC - 24000

ACWP - 13000

BQAC - 500

AQWP - 300

Percentage complete (50%)

OD - 24

BCWS - 14500

Now answer the questions below,

Based on the information above.

1.1. BCAC = R24 000; BCWS = R14 500; ACWP = R13 000; and SV = -2 500.

What is the planned value of the work that was done?

A. R14200

B. R14500

C. R24000

D. R13 000

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!