Question: chedule the following activities using CPM: ACTIVITY IMMEDIATE PREDECESSOR TIME ( WEEKS ) A 5 B A 3 C A 4 D B 6 E

chedule the following activities using CPM:
ACTIVITY IMMEDIATE PREDECESSOR TIME (WEEKS)
A 5
B A 3
C A 4
D B 6
E C D 8
F D 2
G F 4
H E G 3
b. What is the critical path?
multiple choice 1
A-C-E-H
A-B-D-E-H
A-B-D-F-G-H
A-C-E-F-G-H