Question: Schedule the following activities using CPM: ACTIVITY IMMEDIATE PREDECESSOR TIME (WEEKS) A 5 B A 3 C A 4 D B 6 E C%media:cm.png% D

Schedule the following activities using CPM:

ACTIVITY IMMEDIATE PREDECESSOR TIME (WEEKS)
A 5
B A 3
C A 4
D B 6
E C%media:cm.png% D 8
F D 2
G F 4
H E%media:cm.png% G 3

What is the critical path?

multiple choice 1

A-C-E-H

A-B-D-F-G-H

A-C-E-F-G-H

A-B-D-E-H

How many weeks will it take to complete the project?

Which activities have slack, and how much?

multiple choice 2

B 1 week H 2 weeks F 4 weeks.

C 5 weeks F 2 weeks G 2 weeks.

A 2 weeks C 3 weeks F 1 week.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!