Question: Problem 5 - 8 ( Algo ) Schedule the following activities using CPM: ACTIVITY IMMEDIATE PREDECESSOR TIME ( WEEKS ) A 5 B A 3

Problem 5-8(Algo) Schedule the following activities using CPM: ACTIVITY IMMEDIATE PREDECESSOR TIME (WEEKS) A 5 B A 3 C A 4 D B 6 E C D 8 F D 2 G F 4 H E G 3 b. What is the critical path? multiple choice 1 A-C-E-F-G-H A-B-D-F-G-H A-B-D-E-H A-C-E-H c. How many weeks will it take to complete the project?