Question: Problem 5 - 8 ( Algo ) Schedule the following activities using CPM: ACTIVITY IMMEDIATE PREDECESSOR TIME ( WEEKS ) A 5 B A 3
Problem Algo Schedule the following activities using CPM: ACTIVITY IMMEDIATE PREDECESSOR TIME WEEKS A B A C A D B E C D F D G F H E G b What is the critical path? multiple choice ACEFGH ABDFGH ABDEH ACEH c How many weeks will it take to complete the project?