Question: chedule the following activities using CPM: ACTIVITY IMMEDIATE PREDECESSOR TIME ( WEEKS ) A 2 B A 3 C A 5 D B 4 E

chedule the following activities using CPM:
ACTIVITY IMMEDIATE PREDECESSOR TIME (WEEKS)
A 2
B A 3
C A 5
D B 4
E C%media:cm.png% D 7
F D 2
G F 3
H E%media:cm.png% G 7
What is the critical path?
multiple choice 1
A-B-D-E-H
A-C-E-F-G-H
A-C-E-H
A-B-D-F-G-H
How many weeks will it take to complete the project?
Which activities have slack, and how much?
multiple choice 2
Ccm 2 weekssc Fcm 2 weekssc Gcm 2 weeks.
Acm 4 weekssc Bcm 1 weeksc Dcm 2 weeks.
Bcm 2 weekssc Dcm 1 weeksc Ecm 4 weeks.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!