Question: Schedule the following activities using CPM: ACTIVITY IMMEDIATE PREDECESSOR TIME (WEEKS) A 2 B A 5 C A 4 D B 3 E C%media:cm.png% D
Schedule the following activities using CPM: ACTIVITY IMMEDIATE PREDECESSOR TIME (WEEKS) A 2 B A 5 C A 4 D B 3 E C%media:cm.png% D 4 F D 1 G F 1 H E%media:cm.png% G 2 What is the critical path? multiple choice 1 A-C-E-G-H A-C-E-F-G-H A-B-D-E-H A-B-D-F-G-H How many weeks will it take to complete the project? Which activities have slack, and how much? multiple choice 2 Bcm 1 weeksc Hcm 3 weekssc Fcm 2 weeks. Ccm 4 weekssc Fcm 2 weekssc Gcm 2 weeks. Bcm 3 weekssc Ccm 1 weeksc Fcm 4 weeks