Question: Choose: $4600 $4800 $5780 $4940 The resource loading chart or resource graph for a particular type of resource used in a project is given below,

Choose:
$4600
$4800
$5780
$4940
The resource loading chart or resource graph for a particular type of resource used in a project is given below, assuming this resource cost $10/hr and the resource works 8 hours per day. What is the total budget needed for this category of resource B&C D D E F F 2 4 6 8 10 12 14 15Step by Step Solution