Question: The resource loading chart or resource graph for a particular type of resource used in a project is given below, assuming this resource cost $

The resource loading chart or resource graph for a particular type of resource used in a project is given below, assuming this resource cost $20/hr and the resources needed work 5 hours per day only. What is the total budget needed for this category of resource over 16 days of completing this project?
A
A
B&C
D
D
E
F
F
No of Resources
7
6
5
4
3
2
1
2
4
6
8
10
12
14
16
<<===Day
$4600
$3100
$5800
$6200