Question: The resource loading chart or resource graph for a particular type of resource used in a project is given below, assuming this resource cost $20/hr

The resource loading chart or resource graph for

The resource loading chart or resource graph for a particular type of resource used in a project is given below, assuming this resource cost $20/hr and the resources work 5 hours per day only. What is the total budget needed for this category of resource . B&C D D E F F No of Resources 7 6 5 4 3 2 1 2 4 6 8 10 12 14 16