Question: The resource loading chart or resource graph for a particular type of resource used in a project is given below, assuming this resource cost $20/hr

The resource loading chart or resource graph for a particular type of resource used in a project is given below, assuming this resource cost $20/hr and the resources needed work 5 hours per day only. What is the total budget needed for this category of resource over 16 days of completing this project? O $4600 [ $3100 O $5800 O $6200