Question: Consider a 4 - day task with a total planned budget of $ 1 0 0 . The task is scheduled to begin on a

Consider a 4-day task with a total planned budget of $100. The task is scheduled to begin on a Monday, and the status date is set for the following Wednesday at noon. By this point in the timeline (mid-Wednesday). On the first two days of the task, a total cost of $40 per day was incurred. However, despite these expenditures, only 55% of the work has been completed by the status date, as confirmed by progress reports. Given this percentage of completion, the task should have ideally incurred a cost of 55% of the total budget, or $55.
Find the BCWS, ACWP, BCWP.
Discuss the CV, SV, CPI and SPI