Question: Consider a 4 - day task with a total planned budget of $ 1 0 0 . The task is scheduled to begin on a
Consider a day task with a total planned budget of $ The task is scheduled to begin on a Monday, and the status date is set for the following Wednesday at noon. By this point in the timeline midWednesday On the first two days of the task, a total cost of $ per day was incurred. However, despite these expenditures, only of the work has been completed by the status date, as confirmed by progress reports. Given this percentage of completion, the task should have ideally incurred a cost of of the total budget, or $
Find the BCWS ACWP, BCWP
Discuss the CV SV CPI and SPI