Question: Consider a project with the following activities: Activity Predecessor(s) Normal Time Crash Time Normal Cost Crash Cost (Per Day) A ----- 4 4 4000 -----

Consider a project with the following activities:

Activity Predecessor(s) Normal Time Crash Time Normal Cost Crash Cost (Per Day)
A ----- 4 4 4000 -----
B ----- 8 6 8000 1500
C F,D 3 3 600 -----
D B 6 5 900 150
E ----- 7 5 350 100
F A 15 12 9000 900
G B 12 10 1200 200
H G 10 8 1000 150
J L 5 4 1000 300
K E 9 7 900 150
L G,K 11 8 2200 350

Fixed overhead costs per day is $500

Identify the project minimum cost point and the minimum time duration.