Question: Consider a project with the following activities: Activity Predecessor(s) Normal Time Crash Time Normal Cost Crash Cost (Per Day) A ----- 4 4 4000 -----
Consider a project with the following activities:
| Activity | Predecessor(s) | Normal Time | Crash Time | Normal Cost | Crash Cost (Per Day) |
|---|---|---|---|---|---|
| A | ----- | 4 | 4 | 4000 | ----- |
| B | ----- | 8 | 6 | 8000 | 1500 |
| C | F,D | 3 | 3 | 600 | ----- |
| D | B | 6 | 5 | 900 | 150 |
| E | ----- | 7 | 5 | 350 | 100 |
| F | A | 15 | 12 | 9000 | 900 |
| G | B | 12 | 10 | 1200 | 200 |
| H | G | 10 | 8 | 1000 | 150 |
| J | L | 5 | 4 | 1000 | 300 |
| K | E | 9 | 7 | 900 | 150 |
| L | G,K | 11 | 8 | 2200 | 350 |
Fixed overhead costs per day is $500
Identify the project minimum cost point and the minimum time duration.
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts