Question: Consider an activity with these estimates for optimistic, most likely, and pessimistic time: 4 , 1 7 , 5 7 . Find the mean value

Consider an activity with these estimates for optimistic, most likely, and pessimistic time: 4,17,57. Find the mean value of the activity time.
(Please provide answer accurate to two decimal places)