Question: Consider an activity with these estimates for optimistic, most likely, and pessimistic time: 11, 21, 35 . Find the mean value of the activity time.
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
