Question: Consider an activity with these estimates for optimistic, most likely, and pessimistic time: 4, 22, 41. Find the mean value of the activity time
Consider an activity with these estimates for optimistic, most likely, and pessimistic time: 4, 22, 41. Find the mean value of the activity time