Question: Consider the following Activity - On - Node ( AON ) project ( activity completion times are in days ) . it is also a
Consider the following ActivityOnNode AON project activity completion times are in days
it is also a project network showing where node A is starting node and node F is the destination node with different network layout. The numbers above each node indicate the duration time to finish the each node.
Refer to the figure. What is the slack time, in days, associated with activity D
A
B
C
D
E
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock