Question: Consider the following data for a project to install a new server at the Northland Pines High School and calculate the critical path for this

Consider the following data for a project to install a new server at the Northland Pines High School and calculate the critical path for this project.
\table[[Activity,Activity Time (days),Immediate Predecessor(s)],[A,2,-],[B,4,A],[C,5,A],[D,2,B],[E,S,B],[F,1,B, C],[G,8,D, E]]