Question: Consider the following data for MRP. Develop the material requirements plan for item B and C, and answer questions 32-36. MPS start: End item Week
Consider the following data for MRP. Develop the material requirements plan for item B and C, and answer questions 32-36. MPS start: End item Week 1 Week 2 Week 3 Week 4 Week 5 Week 6 A 120 80 Bill of materials: End item A is made of 1 unit of item B. Item B is made of 2 units of item C. MRP-related information for each item: Item Leadtime (weeks) Lot sizing Safety stock On-hand inventory Scheduled receipts B 1 L4L 0 30 60 in week 1 C 2 FOQ (50) 20 80 None
What is the gross requirement for item B in Week 3?
What is the projected available balance of item B at the end of week 1?
What should be the planned order release for item B in week 2?
What is the gross requirement for item C in Week 4?
What should be the planned order release for item C in week 2?
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
