Question: Consider the following data for MRP. Develop the material requirements plan for item B and C, and answer questions below MPS start: End item Week
Consider the following data for MRP. Develop the material requirements plan for item B and C, and answer questions below
MPS start:
| End item | Week 1 | Week 2 | Week 3 | Week 4 | Week 5 | Week 6 |
| A |
|
| 120 | 80 |
|
Bill of materials:
- End item A is made of 1 unit of item B.
- Item B is made of 2 units of item C.
MRP-related information for each item:
| Item | Leadtime (weeks) | Lot sizing | Safety stock | On-hand inventory | Scheduled receipts |
| B | 1 | L4L | 0 | 30 | 60 in week 1 |
| C | 2 | FOQ (50) | 20 | 80 | None |
Question
What is the gross requirement for item B in Week 3?
Group of answer choices
0 unit
80 units
120 units
200 units
240 units
What is the projected available balance of item B at the end of week 1?
Group of answer choices
30 units
60 units
90 units
100 units
240 units
What should be the planned order release for item B in week 2?
Group of answer choices
0 unit
30 units
80 units
170 units
250 units
Question
What is the gross requirement for item C in Week 4?
Group of answer choices
0 unit
80 units
160 units
200 units
240 units
Question
What should be the planned order release for item C in week 2?
Group of answer choices
0 unit
80 units
160 units
200 units
240 units