Question: Consider the following network for a small project. All times are in weeks. a. Assume activity A has an optimistic duration estimate of 2 weeks,

Consider the following network for a small project. All times are in weeks. a. Assume activity A has an optimistic duration estimate of 2 weeks, a most likely estimate of 4 weeks, and a pessimistic estimate of 12 weeks. What would be the PERT estimate for this task? Show your work/calculations to get full credit. (HINT: The PERT formula is Time estimate =(( optimistic time +(4X most likely time )+ pessimistic time ))/6