Question: Consider the following project: Activity Immediate Predecessors Durations (weeks) 5 A B A 3 A 2 D B 3 E 7 F B,C 3 G

Consider the following project: Activity

Consider the following project: Activity Immediate Predecessors Durations (weeks) 5 A B A 3 A 2 D B 3 E 7 F B,C 3 G 6 D, E . 2 Which one of the following would expedite the project? Multiple Choice Expediting H by 1 week Expediting D by 1 week Expediting F by 1 week Expediting G by 1 week O