Question: Project management (3) Consider the following project: Activity Immediate Predecessors Durations (weeks) 4 A B D E F G B , D.E 3 2 3

Project management (3) Consider the following
Project management (3) Consider the following project: Activity Immediate Predecessors Durations (weeks) 4 A B D E F G B , D.E 3 2 3 8 3 7 2. Which one of the following would expedite the project? Expediting B by 1 week Expediting E by 2 weeks Expediting F by 1 week Expediting D by 2 weeks