Question: Consider the following project. Activity Immediate Processor Activity Time ( days ) A - 6 B - 8 C A , B 5 D B

Consider the following project.
Activity Immediate Processor Activity Time (days)
A -6
B -8
C A, B 5
D B 4
E C 7
F C, D 3
G D 6
H E, F, G 5
Determine the slack for activity F.
Consider the following project.
Activity Immediate Processor Activity Time (days)
A -6
B -8
C A, B 5
D B 4
E C 7
F C, D 3
G D 6
H E, F, G 5
Determine the slack for activity F.
3 days